LEGAL FRAMEWORK AND GOVERNMENT REQUIREMENTS

In accordance with the terms of the James Bay and Northern Quebec Agreement ( JBNQA ) , the Chapter   II of the EQA (RSQ, Q-2), provides for specific provisions applicable to the northern regions of Québec. The applicable environmental assessment procedures differ, in particular, through the active participation of the Crees and Inuit who reside there.

In the region in which lies the Nunavik Nickel Project, which is the area north of the 55th   At the same time, the JBNQA created the Kativik Environmental Advisory Committee (KEAC). The KEAC oversees the application and administration of the environmental protection plans provided for in the JBNQA. On the other hand, the preliminary assessment and the project review are done by the KEQC.

The Nunavik Nickel Project is one of the projects covered by the Environment Quality Act . It is therefore necessarily subject to the evaluation process and review of environmental impacts and the social environment, under the EQA as well as to regulations on assessment and review of environmental impacts and the social milieu in the territory of James Bay and Northern Quebec

In accordance with the planned environmental assessment procedure, Canadian Royalties Inc. conducted an environmental and social impact assessment in 2007 ( ESIA, 2007 ) for theNunavik Nickel Project ( PNNi ) .

 

ENVIRONMENTAL POLICIES

Canadian royalties has adopted an environmental and social responsibility policy. This policy constitutes a basis for formulating more specific commitments to certain environmental components. We adhere to the principles promoted by the Mining Association of Canada’s Towards Sustainable Mining initiative and recognize the importance of:

  • Biodiversity Conservation
  • Responsible water use
  • Combating and adapting to climate change
  • Tailing responsible management

 

Biodiversity conservation policy

Biodiversity conservation policy

Water stewardship policy

Water stewardship policy

Climatic strategy

Climatic strategy

Tailing Management Policy

Tailing Management Policy

 

ENVIRONMENTAL MANAGEMENT

At the completion of the environmental impact assessment process, Canadian Royalties Inc. has obtained a global certificate of authorization, which includes a series of environmental follow-ups to be put in place. The size of the PNNi makes the occurrence of some residual impacts inevitable, which is why several components of the natural environment are subject to mitigation measures and rigorous environmental monitoring. The mitigation measures put in place are intended to reduce and control impacts on the entire natural environment.

Canadian Royalties Inc.'s mission is to optimize the environmental management of its activities in order to protect and conserve the natural environment hosting the Nunavik Nickel Project

Canadian Royalties Inc. has an environmental management system based, state and federal regulations and guidelines, as well as the requirements are issued authorization certificates and permits. This system include a series of environmental procedures to properly manage environmental issues

PRO-NENV-1211-01 Response to an Environmental Incident
PRO-NENV-1606-01 Management of Residual Materials
PRO-NENV-1211-03 Management of Residual Hazardous Materials
PRO-NMIN-1505-01a Procedure for the monitoring of mining facilities, and the management of tailings, waste rock and water
PRO-NENV-1712-01 Reporting of Air Contaminant Emission
PRO-NENV-1211-05b Wildlife Management

 

NNIP ENVIRONMENTAL MONITORING PROGRAM

The PNNi Environmental Monitoring Program takes into account all Canadian Royalties Inc.'s commitments, all obligations, conditions and requirements of the appropriate authorities as well as applicable directives and regulations. Updates are made to add the requirements of the latest authorizations. The programme includes, among others, the following aspects:

  • Monitoring the quality of the water in the receiving environment and the final effluent;
  • Biological and physical monitoring of the receiving environment (fish populations, benthic invertebrate communities, environmental variables and sediment quality);
  • Monitoring of emissions and dust dispersions;
  • Monitoring the quality of drinking water;
  • Monitoring the stability of culverts and the free movement of fish;
  • Monitoring of the Lac Bombardier fish population;
  • Wildlife monitoring, including caribou
  • Follow-up of visual and sound impacts in the Pingualuit National Park.

 

MITIGATION AND PROGRESSIVE REHABILITATION

The size of the PNNi makes the occurrence of some residual impacts inevitable, which is why several components of the natural environment are subject to rigorous mitigation measures and environmental monitoring, based on regularly revised management procedures by Canadian Royalties Inc.

Mitigation measures are put in place to minimize and control impacts on the entire natural environment. For example :

  • The application of dust suppressants in dry and windy weather on roads to avoid the increase of dust in the air caused by road transport.
  • The prohibition of machinery moving outside the boundaries of work areas to protect terrestrial and wetland habitats and plants of special status or rare species.
  • The installation of culverts so that it does not impede the flow of water and thus allow the free movement of fish.
  • Safe and complete management of spills on all PNNi facilities.

 

NNiP mitigation measures

NNiP mitigation measures

 

PUBLIC REPORTS

Canadian Royalties practices transparency and public accountability; Reports on our company's performance in maintaining biodiversity, water stewardship, greenhouse gas emissions and community relations are available.

The summary of the annual environmental monitoring report is also available.

 

Report SER - 2025

Report SER - 2025

Report SER - 2024

Report SER - 2024

Report SER - 2023

Report SER - 2023

 

Annual Environmental Monitoring Report - 2025

Annual Environmental Monitoring Report - 2025

Annual Environmental Monitoring Report - 2024

Annual Environmental Monitoring Report - 2024

 

Summary of Rehabilitation Plans Nunavik Nickel Project (NNiP)

Summary of Rehabilitation Plans Nunavik Nickel Project (NNiP)

Public consultation report - Communities of Puvirnituq, Kangiqsujuaq and Salluit

Public consultation report - Communities of Puvirnituq, Kangiqsujuaq and Salluit

Climate Change Adaptation Plan

Climate Change Adaptation Plan

Addendum to the Environmental and Social Impact Study

Addendum to the Environmental and Social Impact Study - Inukshuk

Headquarters

800, René-Lévesque W.
Suite 410
Montreal (Quebec) H3B 1X9
Phone: 514 879-1688
Toll free: 877 879-1688
Fax: 514 879-1795
© Canadian Royalties inc. - 2026
In touch with communities